Construction Update - May 2021
11:30AM May 04, 2021
We have now activated 2 of the 8 zones in our new Southeast
Elbert construction project. The second
zone on Lincolnton Hwy.—Ricetown—Cooter Creek—Hester Road was connected in
early April. We now have added nearly
100 new subscribers to ElbertonNET in these 2 zones in the last 2 months.
Now we are ready to activate the third zone, which will be the
Eastern Calhoun Falls Hwy.—Dixon McCall—Welcome Church Roads neighborhood. We have connected this node to the network
and are completing a testing and configuration period now. Tomorrow, May 5, we will begin to contact
pre-registered and pre-paid supporters to schedule installation appointments
starting the week of May 10.
Construction continues on the remainder of the project, and
there will be 5 zones left to connect through the spring and into the
summer. Likely the Bakers Ferry—Wahatchee
Creek area will be next to connect in late May based on the number of pre-paid
registrations that we have received.
We look forward to serving you soon with great high speed
Internet, TV, and digital phone!